The City of Temple is seeking bids for the repair of the foundation issues associated with the elevator/office addition at Clarence Martin Gym. The scope of work includes providing all labor, equipment, materials, tools, and supervision required to complete the repairs. The total base bid for the project is $29,995.00. The contract was awarded to Wilson Construction Services, LLC. Key aspects of the project include the repair of the foundation, the provision of all necessary labor and materials, and the completion of the work in accordance with the specifications and addenda.
• The project involves repairing the foundation issues associated with the elevator/office addition at Clarence Martin Gym.
• The scope of work includes providing all labor, equipment, materials, tools, and supervision required to complete the repairs.
• The total base bid for the project is $29,995.00.
• The contract was awarded to Wilson Construction Services, LLC.
• The project includes three addenda, which are acknowledged by the awarded vendor.