The Leon County School Board solicited bids (ITB 2420‑2025) to replace the roof on Building 9 of Fort Braden K‑8 School. After a mandatory pre‑bid conference and bid opening on June 4 2024, the Board issued a formal award recommendation on July 2 2024 selecting Harrell Roofing, LLC. The contractor must be ready to start by July 18 2024 and complete the work within roughly 60 days. The project is a lump‑sum, competitive sealed‑bid procurement for a full metal‑roof replacement, including removal of existing roofing, disposal, installation of new insulation, underlayment, and metal panels, with a warranty provision. No budget figure is disclosed in the public documents.
• Scope: complete removal and replacement of the metal roof on a K‑8 school building.
• Procurement: full‑open competition, sealed‑bid, lump‑sum award to a single vendor.
• Timeline: bids due June 4 2024; award recommendation July 2 2024; work to begin ≤ July 18 2024 and finish ≈ early September 2024.