The City of Roseville is seeking bids for the West Side Tank and Pump Station Project, which includes the construction of two six million gallon storage tanks and an accompanying pump station. The project requires the removal of unsuitable soils from the site, hauling off the material, and ensuring interim and long-term positive site drainage. The bid summary sheet lists three bidders, but the document does not specify which vendor was awarded the contract. The bid amounts range from $220,000 to $420,160.
• The project is located in Roseville, California
• The bid posting date was June 12, 2017
• The bid submission date was July 3, 2017
• The bid bond is required
• The contract value is estimated to be around $420,160