The Durham Pentz Rd. HSIP Cycle 5 Safety Project involves clearing and grubbing, traffic control, microsurfacing the roadway, applying thermoplastic traffic striping and thermoplastic traffic markings. The project is located on Durham Pentz Road between Highway 99 and Highway 191. The engineer's estimate for the project is $509,371.50.
• The project was advertised on July 2, 2015, and bids were opened on July 23, 2015.
• Two vendors, VSS International and Pavement Coatings Company, submitted bids, but all bids were rejected.
• The project requires various tasks, including clearing and grubbing, traffic control, microsurfacing, and applying thermoplastic traffic striping and markings.
• The project has a detailed breakdown of the estimated costs for each task, with a total estimated cost of $509,371.50.