The North Red Hills Campground Electric Project at Seminoe State Park is a project that was put out for bid by the State of Wyoming, Department of Administration and Information/Procurement Section. The bid was for the installation of electric services at the campground. The bid was rejected due to all bid(s) received coming in over budget. The project had a mandatory pre-bid meeting, and all questions were required to be submitted to the engineer. The bid documents and addenda were available for download on the Public Purchase website.
• The project is located at Seminoe State Park in Carbon County, Wyoming.
• The bid was published on April 9, 2019, and the deadline for submission was April 25, 2019.
• The bid was rejected on May 1, 2019, due to all bid(s) received coming in over budget.
• The project had a mandatory pre-bid meeting on April 18, 2019.
• All questions were required to be submitted to the engineer, [email protected].