The contract is for the construction of the VAV replacement phase 5 at the Salt Lake Community College - Larry H. Miller Campus in Sandy, Utah. The project involves upgrading the VAVs and controls for the campus, including the PSET, Dorm, and MCPC buildings. The construction cost estimate is $1,480,050.00. The contract was awarded through an invitation for bid (IFB) process, and the bid documents were available on the Utah Public Procurement Place website. The contract has a completion date of 8/15/2024. Key aspects of the project include:
• Upgrade of VAVs and controls for the campus
• Construction cost estimate of $1,480,050.00
• Completion date of 8/15/2024
• Invitation for bid (IFB) process
• Bid documents available on the Utah Public Procurement Place website
• Project point of contact: Erik Worley, (801) 918-8181, [email protected]