This contract involves the full replacement of the domestic water distribution system for Building #4 at Lively Technical College. The work includes demolition of existing below‑slab piping, removal of all above‑ground water lines, installation of new overhead Type L copper press‑fit piping, routing through restroom walls, concrete and CMU wall repairs, system testing, and provision of new hose bibs. An optional bid item allows replacement of plumbing fixtures such as toilets and urinals. The project must comply with the 2023 Florida Building Code, NFPA 70, and related standards, and requires the contractor to hold a Florida plumbing license, a pre‑qualification certificate, and appropriate bonding and insurance.
• Mandatory pre‑bid conference July 1 2026; sealed bids due July 29 2026.
• Earliest start by August 26 2026, with substantial completion required by December 31 2026.
• Awarded to Keith McNeil Plumbing Contractor, Inc., pending final approval.