Awarded vendors
- Pellco Construction Inc
Description
This contract is for the construction of a new double-bank electrical distribution substation on District property in Snohomish County, WA. The project includes clearing, grubbing, and stripping, temporary erosion and sedimentation controls, earthwork, concrete block retaining wall, storm drainage conveyance systems, and more. The engineer's estimate for the project is $2,338,500.00. The contract was awarded to Pellco Construction Inc.
• The project involves constructing a new substation on District property.
• The engineer's estimate for the project is $2,338,500.00.
• The contract was awarded to Pellco Construction Inc.
• The project includes various construction activities such as clearing, earthwork, and storm drainage conveyance systems.
• The contract was bid through the Public Purchase website, with bids submitted electronically.
• A pre-bid conference was held on June 9, 2020, with an optional site visit at 1 pm.