This contract concerns the replacement of multiple storm‑water management (SWM) culverts across Snohomish County, Washington. The project includes extensive earthwork, drainage installation, road surfacing, erosion control, and ancillary structures such as guardrails, fencing, and geotextile placement. Five pre‑qualified contractors submitted bids; the county ultimately awarded the contract to Reece Construction for a lump‑sum price of $999,999.99. The engineer’s estimate for the work was $1,467,454.87, indicating the award is roughly 68% of the estimated cost. The contract is funded by County SWM and REET funds and incorporates mandatory credits for job‑mix, compaction, and aggregate compliance, as well as an apprenticeship incentive. Key points:
• Scope: Culvert replacement, road base, surface, erosion control, and related utilities.
• Value: Awarded at just under $1 M (≈ 68% of engineer’s estimate).
• Schedule: Bid deadline 3 Mar 2026; award 18 Mar 2026; no explicit start or completion dates provided.
• Procurement: Full open competition; single‑award to Reece Construction.