This contract is for the rehabilitation of Taxiway A at the Orlando Sanford International Airport. The contract was awarded to Halifax Paving, Inc. for a total sum of $6,589,268.00. The project involves the furnishing of all materials required and the performance of all work and labor necessary to complete the project in a satisfactory and workmanlike manner. The contract includes provisions for payment, termination, and dispute resolution. The contractor is required to comply with all applicable laws and regulations, including those related to labor, safety, and environmental protection.
Some key points of this contract include:
• The contract duration is 63 days
• The total contract value is $6,589,268.00
• The contractor is required to furnish all materials and perform all work necessary to complete the project
• The contract includes provisions for payment, termination, and dispute resolution
• The contractor must comply with all applicable laws and regulations