The contract is for the North Vineyard Station Open Space Preserve Trail and Landscaping Project - Elder Creek Phase 1B. The project includes installing native plantings, irrigation, and multi-use trails within an open space preserve creek corridor. The contract was awarded to Bobo Construction, Inc. with a total bid of $2,888,706.00. The project includes a minimum 5-year monitoring period. Key aspects of the project include:
• Installation of native plantings over approximately 16.8 acres
• Installation of approximately 26,000 feet of irrigation pipe
• Installation of approximately 2,185 feet of paved bicycle path
• Installation of approximately 1,510 feet of equestrian trail
• A low flow creek trail crossing
• Landscaping of the creek section as a natural riparian corridor
• A minimum 5-year monitoring period after plant installation