The contract is for the Taxiway G Extension project at the Tampa International Airport. The project involves the construction of a new taxilane and has a duration of approximately 755 days. The contract was awarded to Cobb Site Development, Inc. and has a total value of $1,627,989.04. The contract includes provisions for change orders and claims, and the vendor is required to provide all outstanding obligations to the owner under the contract, including close-out obligations, punch list items, warranty, and correction of defective and non-conforming work. Key aspects of the contract include:
• The contract sum is $1,627,989.04
• The contract duration is 755 days
• The project involves the construction of a new taxilane
• The vendor is required to provide all outstanding obligations to the owner under the contract
• The contract includes provisions for change orders and claims