The contract is for the Red Rock Booster Pump Station Upgrades project, which involves pumping, electrical, and mechanical upgrades to increase the capacity of the existing station. The project includes new pumps, variable frequency drives, a new floor, ventilation system, and new process piping. The engineer's estimate for the project is $1,200,000.00, and the bidder's base bid is $1,150,000.00. The contract was awarded to Action Mechanical. Key aspects of the project include:
• Pumping upgrades
• Electrical upgrades
• Mechanical upgrades
• New pumps and variable frequency drives
• New floor and ventilation system
• New process piping