The Town of Chapel Hill contracted Ruston Paving Co, Inc. to replace and upgrade the parking lot at Cedar Falls Park, installing new asphalt pavement, concrete wheel stops, and ADA‑compliant striping. The work includes milling existing surface, proof‑rolling, laying a 2.5‑in. binder course and a 1.5‑in. surface course, tie‑ins to existing pavement, and installing reflective‑glass‑bead markings. The contract is a single‑award, unit‑price construction project with a 120‑day performance period and liquidated damages of $250 per day for delays.
• Scope: mill‑regrade‑pave, wheel stops, striping, and seal‑coat for ~6,265 sq yds of parking area.
• Timeline: award June 11 2026; work to be substantially completed by mid‑September 2026.
• Procurement: full and open competition with mandatory pre‑bid conference; electronic bid submission only.