This contract covers the demolition of existing terrazzo flooring and the installation of new quartz tile flooring in the central concourse of William P. Hobby Airport. The work includes substrate preparation, expansion‑joint control, temporary facilities, and coordination to keep the airport operational, with a required substantial‑completion window of 140 calendar days. The project is funded by the City of Houston and was awarded to JLA Construction Solutions at a contract value of approximately $3.1 million. Key requirements include meeting a 16.4 % MWBE participation goal, adherence to pay‑or‑play provisions, and compliance with city‑specified bonding, insurance, and performance standards.
• Demolition of existing terrazzo and preparation of substrate for quartz tile.
• Installation of engineered quartz tile, including expansion joints and related MEP coordination.
• Strict schedule and “quiet” construction constraints to maintain airport operations.