This contract is for the update of Ort equipment at the New Gloucester/West Gardiner Barrier Toll Plaza, located at mile 67.0 SB and NB and mile 100.0 SB and NB. The work includes removing the top three inches of the ORT concrete roadway slab, replacing it with a three-inch concrete wearing surface, and reinstalling new toll sensor loops. The contract also includes the relocation of existing ORT toll equipment, installation of new toll equipment, and replacement of lane use signals. The project is expected to be completed by April 16, 2021. The contract was awarded to Scott Construction Corporation.
• The project involves the removal and replacement of concrete roadway slabs
• The project includes the installation of new toll sensor loops and relocation of existing ORT toll equipment
• The project requires the replacement of lane use signals at the New Gloucester Barrier Toll Plaza cash lanes
• The project is expected to be completed within a year of the bid date
• The contract was awarded to Scott Construction Corporation