This contract concerns the erection, rental, and dismantling of a high‑bridge scaffolding system beneath the Fairmount Bridge in Cleveland. The county requires a 28‑day rental with the scaffolding erected by October 1 2022, including a solid top deck, guard rail, ladder access, anchored jacks, and beam‑clamp connections. The solicitation was posted on a very short 8‑hour window, and quotes were to be submitted via email. The award amount recorded is $5,819.74, but the vendor’s identity is not disclosed. The work is time‑critical, mission‑critical, and limited to vendors able to meet the tight erection deadline and safety requirements. Registration with the Cuyahoga County Inspector General’s Office and the Lawson electronic purchasing system is mandatory.
• Scope: Scaffold erection (6 ft × 14 ft × 12 ft), safety features, 28‑day rental, dismantling.
• Critical deadline: Erection must be completed by 1 Oct 2022.
• Procurement: Extremely short posting window; likely sole‑source/limited competition.
• Value: Awarded line shows $5,819.74 (vendor not named).