This contract is for the replacement of twelve rooftop HVAC heat‑pump units (eight at Mark Twain Elementary School and four at Lynwood High School – Bullis Campus). The work includes demolition of existing equipment, installation of new Carrier heat‑pump units, seismic anchoring, hail guards, MERV‑13 filtration, condensate‑drain upgrades, electrical connections, testing, adjusting, balancing, and commissioning. The district supplies the equipment, and the contractor will handle all handling, transport, installation, and integration with the existing building control systems. The project is funded by the Lynwood Unified School District and follows California public‑work prevailing‑wage and DVBE requirements.
• Scope: full HVAC replacement on two K‑12 school roofs (12 units total).
• Schedule: start June 22 2026, substantial completion July 21 2026 (≈30 days).
• Award: Allison Mechanical Inc. identified as low‑bidder ($254,000) with a Notice of Intent dated April 21 2026; contract documents due by April 26 2026.