The contract is for the removal of existing exterior ductwork from the SLP building to the precipitator and the installation of new duct on the exterior of the SLP building, bypassing the precipitator. The bid was rejected from Egan Company. Key points to consider include:
• The project involves the removal and installation of ductwork
• The bid was rejected from Egan Company
• The project is located at the Silver Lake Plant in Rochester, MN
• The bid contact is Mona Hoeft
• The bid was due on March 8, 2023, at 3:00:00 PM EST