The contract is for the conversion of the Interchange 103 Barrier Toll Plaza to an Open Road Tolling (ORT) system. The project includes the construction of two northbound and two southbound ORT lanes, as well as three northbound and three southbound cash/E-ZPass lanes. The work also includes the installation of tolling provisions in the tunnel, canopy, and toll booth, maintenance of traffic, and all other work incidental thereto in accordance with the Plans and Specifications. The contract is being awarded to Sargent Corporation, a private company that specializes in construction and engineering services.
Some key features of the project include:
* Construction of new lanes and ramps
* Installation of tolling equipment
* Maintenance of traffic
* Construction of a precast pedestrian tunnel for employee access and utilities
* Construction of an Administration Building and access road
* Reconfiguration of Exit 51 ramps and I-295 Northbound ramp
* Demolition of existing toll plaza and reconstruction of the mainline to accommodate approach and departure grade and alignment differentials at the modified plaza.
The project is expected to improve the safety and efficiency of the toll plaza, and to reduce congestion and wait times for motorists.