The contract is for the reroofing of the FSU Research Complex, which includes cleaning the existing sloped metal roofing system, refastening and sealing all exposed perimeter fasteners, raising existing rooftop equipment, vents, and VTRs to a minimum of 10" above the finished roof surface, and installing a new 60 mil KEE single-ply roofing system with a 20-year NDL warranty. The contract was awarded to Advanced Roofing for a total of $422,332.00. The project also includes an additive alternate for removing existing stucco finish and installing architectural wall panels, flashings, and trim. Key information to consider when evaluating this contract includes the scope of work, the materials and equipment required, and the timeline for completion.
• The contract includes a detailed scope of work, which outlines the specific tasks and requirements for the project.
• The contract specifies the materials and equipment required for the project, including a 60 mil KEE single-ply roofing system and 3" rigid insulation board.
• The contract includes a timeline for completion, with the bid submission date listed as 3/20/2020.
• The contract was awarded to Advanced Roofing, who submitted the lowest bid of $422,332.00.
• The contract includes an additive alternate for removing existing stucco finish and installing architectural wall panels, flashings, and trim.