The contract is for the replacement of approximately 1,900 linear feet of asbestos cement water main with new ductile iron water main. The scope of work includes removal of asbestos cement water main, installation of new hydrants, valves, fittings, and services, as well as hardscape and landscape restoration. The engineer's estimate for the project is $1,486,294.95. The contract was awarded to Fury Site Works, Inc. with a total bid price of $1,172,063.91.
• The project involves replacement of water main and installation of new hydrants and valves
• The scope of work includes hardscape and landscape restoration
• The engineer's estimate for the project is $1,486,294.95
• The contract was awarded to Fury Site Works, Inc. with a total bid price of $1,172,063.91