This contract concerns the first phase of improvements to Dog River Park in Mobile, Alabama, focusing on the construction of new sidewalks, paving, and bleacher structures. The City of Mobile issued a sealed‑bid solicitation (PR‑116‑17) that required mandatory attendance at a pre‑bid conference on May 22 2018. Bids were due by May 30 2018, and the contract was ultimately awarded to Aeiker Construction Corporation for a total of $62,980. The project is tax‑exempt and follows a traditional competitive bidding process.
• Scope: Install sidewalks, pave park areas, and build bleacher facilities within Dog River Park (Phase 1).
• Procurement: Open, sealed‑bid competition with mandatory pre‑bid attendance; award made to a single vendor.
• Value: Fixed‑price award of $62,980, indicating a lump‑sum contract for a relatively small municipal improvement project.