The contract is for the installation of an electric vault and conduit system at the Westside Substation Feeder Exits. The project includes the installation of concrete encased power duct banks, directional boring, and power vault installation. The contract was awarded to Elcor Construction and A&A Electric. The evaluated total for the contract is $150,242.00 for Elcor Construction and $216,300.00 for A&A Electric.
• The project includes the installation of 60 ft of concrete encased power duct bank at a cost of $6,657.00 for Elcor Construction and $9,000.00 for A&A Electric.
• The project includes the installation of 70 ft of power duct bank at a cost of $5,561.50 for Elcor Construction and $10,150.00 for A&A Electric.
• The project includes the installation of 30 ft of power duct bank at a cost of $1,833.00 for Elcor Construction and $3,600.00 for A&A Electric.
• The project includes the installation of 2 power vaults at a cost of $35,990.00 for Elcor Construction and $45,600.00 for A&A Electric.
• The project includes the installation of 1,220 ft of directional boring at a cost of $21,838.00 for Elcor Construction and $18,300.00 for A&A Electric.
• The project includes the provision of labor and equipment, including foreman, equipment operators, laborers, track hoes, dump trucks, and trenchers.