This contract involves the installation of a new 165 kW, skid‑mounted diesel engine‑generator at the Chignik Lagoon community in Alaska. The owner (Alaska Energy Authority) furnishes the generator, while the contractor is responsible for all mechanical and electrical installation work, demolition of the existing engine‑coolant system, installation of a new coolant system (optional alternate), testing, commissioning, and site cleanup. The project required coordination with the local village council and school district, barge access for material delivery, and adherence to state and federal wage, safety, and insurance requirements. The schedule was compressed, with equipment availability by mid‑August 2018 and final completion (including warranty) by late October 2019.
• Install owner‑furnished 165 kW generator and associated controls, piping, and electrical work.
• Optional Additive Alternate #1: demolish existing coolant system and install a new thermostatic coolant system.
• Meet tight milestones: substantial completion of base‑bid by 20 Sep 2018, final completion by 27 Sep 2018, and warranty end by 25 Oct 2019.