The City of Independence, Missouri, seeks to improve the gravel roadways at the Courtney Bend Water Production Plant. The existing gravel roadways around the production plant and south well field are in need of repair and rehabilitation. A new gravel roadway is required in the North well field where there is currently no prepared road surface. The project was awarded to KAT EXCAVATION. The contract involves the construction of gravel roadways to standards able to support heavy construction and service vehicle traffic.
• The project includes the repair and rehabilitation of existing gravel roadways
• A new gravel roadway is required in the North well field
• The roadways must be constructed to support heavy construction and service vehicle traffic
• The project was awarded to KAT EXCAVATION
• The City of Independence, Missouri, is the agency responsible for the project