The University of Wyoming is seeking a contractor to remove university-owned buildings and clear structures/improvements on four residential lots. The project includes surface preparation, roto-mill surface, lighting, and landscaping. The estimated project completion date is November 18, 2022. The contractor will be responsible for removing asbestos prior to demolition. The bid results show BIG HUHNKS EXCAVATION as the winning bidder with a base bid of $777,409.96.
• Removal of university-owned buildings and clearing of structures/improvements on four residential lots
• Surface preparation, roto-mill surface, lighting, and landscaping
• Asbestos abatement prior to demolition
• Estimated project completion date: November 18, 2022
• BIG HUHNKS EXCAVATION is the winning bidder with a base bid of $777,409.96