This contract provides for the mill‑and‑overlay of approximately 30 lane‑miles of Denver’s local, collector, and arterial streets. The scope includes full‑width roto‑milling, placement of hot‑mix asphalt (including SMA on arterial sections), removal and replacement of ground signs and inlet grates, traffic‑control services, pavement markings, and related public‑information work. The City set a 17 % MWBE participation goal, and the contract was awarded on a unit‑price basis with an estimated total value of $2.6 million. The work is governed by Denver prevailing‑wage requirements and requires a right‑of‑way occupancy permit.
• Mill and overlay approximately 30 lane‑miles of city streets (local, collector, arterial)
• Unit‑price quantities include 245,000 SY of asphalt removal, 17,300 TON of HBP asphalt, 2,050 TON of SMA, plus sign, marking, and traffic‑control items
• Awarded to Brannan Sand and Gravel Company, LLC for $2,607,987.50 with MWBE goal of 17 % and prevailing‑wage compliance