The contract is for the replacement of an existing sewer main on Mariposa Avenue. The initial contract term was from June 17, 2024, to December 14, 2024, with an initial contract amount of $770,770.00. The contract was amended to extend the term by 55 calendar days, with a new end date of February 8, 2025. The contract includes provisions for successors and assigns, and the entire agreement is binding upon the parties. The key points of the contract include:
• Replacement of existing sewer main on Mariposa Avenue
• Initial contract term: June 17, 2024, to December 14, 2024
• Initial contract amount: $770,770.00
• Contract extension: 55 calendar days
• New end date: February 8, 2025
• Provisions for successors and assigns
• Entire agreement is binding upon the parties