This solicitation sought the supply of steel poles required for the termination phase of the Ohme Substation project. The agency estimated a budget of $130,000 and received two competitive bids: Wireless Structures Consulting Inc. (dba Western Utility Telecom Inc.) offered $60,490, while Mica’s Steelworks Inc. bid $141,429. Both bidders complied with the mandatory bid‑bond requirement. No award information was disclosed, and the contract remains unawarded.
• Scope: Procurement of steel poles for substation termination.
• Budget vs. bids: One bid under budget, one over budget.
• Competition: Open competition with two qualified bidders.
• Status: No vendor awarded; award data omitted.