The contract is for Public Works Facility Stormwater Drainage Improvements, which includes providing all necessary labor, materials, equipment, and supervision for the project. The contract was awarded to Barracuda Building Corporation, and the bid price was $58,948.00. The project has a desired completion time of 90 days. Key aspects of the project include mobilization, erosion control, base limerock, asphalt concrete, and pipe culvert installation.
• The project involves stormwater drainage improvements at the Public Works Facility.
• The contract was awarded through an Invitation to Bid (ITB) process.
• The bid price includes all necessary labor, materials, equipment, and supervision.
• The project has a desired completion time of 90 days.
• The contract includes various line items, such as mobilization, erosion control, and pipe culvert installation.