The contract is for the construction of an asphalt taxiway extension at Peter O. Knight Airport. The project includes associated drainage improvements and airfield lighting and signage installation. The contract was awarded to Cobb Site Development, Inc. for a total amount of $1,399,860.12. The project consists of approximately 4,500 CYD of earthwork and grading, 600 SY of asphalt pavement demolition, 7,750 SY of asphalt taxiway construction, and other related work. The contract duration is 743 days, starting from May 2, 2019, and ending on June 6, 2021. Key points to consider when evaluating the similarity of this contract to others include the type of construction work, the location, and the contract duration and value.