This contract involves the complete replacement of the existing hot water booster pump system at the Snohomish County Jail. The scope requires the contractor to provide all labor, parts, and supplies necessary to remove the old pump, properly dispose of it, and install a new booster pump package. The work is classified as a Small Works project, indicating a relatively limited scope and budget. The solicitation was posted on February 25 2019, with a bid deadline of March 14 2019, and the award was announced on April 18 2019. No vendor information is publicly available.
• Scope: Remove and dispose of existing hot‑water booster pump, install new booster pump package.
• Procurement Type: Small Works (likely a single‑source or limited competition procurement).
• Key Dates: Available 2/25/2019, Bid Due 3/14/2019, Award 4/18/2019.