This contract is for the installation of scoreboard foundations at six middle school football/soccer fields in Topeka, Kansas. The scope of work includes the installation of foundations, structural systems, and new scoreboards at each of the six middle schools. The actual scoreboards and electrical work have been purchased/bid separately. The contract was awarded to GSR Construction and D.F. Osborne, with bids of $35,700.00 and $114,900.00, respectively.
• The contract is for a specific project with a clear scope of work
• The contract was awarded to two vendors, GSR Construction and D.F. Osborne
• The bids for the contract were $35,700.00 and $114,900.00, respectively
• The contract is for a public school system, Topeka Public Schools
• The project involves the installation of scoreboard foundations and new scoreboards at six middle schools