This procurement concerns the rehabilitation and improvement of the Frame Park Formal Gardens Pathway, including irrigation, drainage, grading, and pavement work. The scope lists 22 core line items—traffic control, temporary fencing, removal of existing sidewalks and drainage, grading, base‑course aggregate, limestone screenings, clean‑out drains, PVC storm‑sewer pipe, field stone with geotextile, concrete sidewalk, topsoil/fertilizer/seed, sod, irrigation system installation, and brick edging. Two optional paving alternatives are offered: permeable precast concrete unit pavers and flexible porous pavement, each raising the total bid amount. The base bid totals $174,493, while the alternatives bring the totals to $238,365 and $253,975 respectively. All‑Ways Contractors, Inc. submitted the detailed unit‑price bid, but no award decision is recorded. The solicitation was posted by the City of Waukesha, Wisconsin, and bids were received on 11 April 2025. The project falls under municipal park‑improvement and infrastructure‑renewal activities, involving civil‑construction, drainage, and landscaping services.
• Core civil works: demolition, grading, base course, drainage and storm‑sewer pipe installation.
• Pavement alternatives: standard concrete sidewalk vs. permeable precast concrete or flexible porous pavement.
• Landscape components: topsoil, seed, sod, irrigation system, and brick edging.
• Financials: base bid $174,493; alternatives $238,365 and $253,975.