The contract is for the construction of a new bike/pedestrian trail, "Backcountry", at Cacapon Resort State Park. The vendor, Dirt Endeavors LLC, will provide all materials, equipment, and labor to complete the work in a workmanlike manner. The contract includes a base bid of $757,988.20 and has a duration of 545 days. The scope of work includes the construction of 10.27 miles of mountain bike trails, with various segments and features such as trail hubs, site-crafted compost logs, rock armor, and rock walls. Key points to consider:
* The contract is for a fixed period of 545 days
* The vendor is required to provide all materials, equipment, and labor
* The contract includes a base bid of $757,988.20
* The scope of work includes the construction of 10.27 miles of mountain bike trails
* The contract has various segments and features, such as trail hubs and rock armor