This contract is an Intergovernmental Agreement (IGA) between the Town of Fountain Hills and the Flood Control District of Maricopa County for the design, construction, and operation of the Courtside Villa-Deuce Ct. and Parcel F: Drainage Improvements project. The project aims to reduce flood hazards in the area. The Flood Control District of Maricopa County will fund 75% of the project's design and construction costs, up to a maximum of $1,000,000. The Town of Fountain Hills will be responsible for the remaining 25% of the costs. The project is expected to be completed by June 30, 2024. Key aspects of the contract include:
• Project scope: design, construction, and operation of the drainage improvements
• Funding: 75% by the Flood Control District of Maricopa County, 25% by the Town of Fountain Hills
• Project timeline: expected completion by June 30, 2024
• Contract value: estimated $95,000 for design and construction costs
• Contract parties: Town of Fountain Hills and Flood Control District of Maricopa County