The Sunnyvale Station Rehabilitation Project involves the reconstruction of portions of both existing platforms at the Sunnyvale Train Station. The work includes civil construction, demolition, and removal of pavers, as well as the installation of new platforms, drainage, and site improvements. The contract was awarded to Sposeto Engineering, Inc. for an amount of $753,000. The project is expected to start shortly after the limited notice to proceed is issued. Key aspects of the project include:
• Reconstruction of existing platforms
• Demolition and removal of pavers
• Installation of new platforms and drainage
• Site improvements, including landscaping and irrigation
• Relocation of existing facilities, including mini-high platforms and passenger shelters
• Construction of new curb and gutter, sidewalk, and station access