This contract awards a $715,541 lump‑sum construction project to Belsaas & Smith Construction, Inc. for the Lincoln Avenue Grade Separation Artwork and Elevated Sidewalk improvement in Yakima, WA. The scope covers demolition of existing concrete sidewalks, curbs, and median barriers; installation of new concrete sidewalks, curb ramps, traffic barriers, paint markings, bicycle lane symbols, and a comprehensive public‑art package that includes structural elements, graphic and glass panels, lighting, and a bird deterrent. Environmental compliance is addressed via a required Stormwater Pollution Prevention Plan, and the project requires a 5 % bid bond from the contractor. The procurement was conducted through a sealed‑bid, full‑open competition, with bids opened and the award made on the same day, March 3 2016.
• Total contract value: $715,541 (city‑engineer’s report total)
• Major work categories: demolition, concrete pavement & curb work, traffic control, painting, bicycle lane signage, and public‑art installation
• Procurement method: competitive sealed‑bid, full‑open competition with 5 % bid bond requirement.