This contract is for the construction of a new freight elevator in the terminal at the St. Pete-Clearwater International Airport. The contract was awarded to DS Jordan Construction Inc for a total amount of $369,825.74. The project was completed on October 12, 2023, with some delays due to elevator manufacturer delays, inspection delays, and hurricane Idalia. The contract includes a release of all remaining retainage and final payment to the contractor. Key aspects of the contract include:
• Original agreement amount: $381,731.50
• Change Order No.1: time-only extension due to elevator manufacturer delays
• Change Order No.2: final change order with a decrease in agreement amount by $11,905.76
• Final agreement amount: $369,825.74
• Completion date: October 12, 2023
• Release of all claims by the contractor against the owner