The contract is for the construction of pipeline sections A, B, and C, which includes approximately 73,000 linear feet of 54" pipeline, 75,000 linear feet of 54" pipeline, and 67,000 linear feet of 54" pipeline, as well as horizontal directionally drilled pipelines and a 6 MG ground storage tank. The contract was awarded to Garney Companies Inc. for $84,121,405.00. The project includes pre-bid meetings, addenda, and bid results. The key aspects of the contract include the construction of pipelines, storage tanks, and other related infrastructure.
• The contract includes the construction of approximately 215,000 linear feet of 54" pipeline.
• The contract includes the construction of horizontal directionally drilled pipelines.
• The contract includes the construction of a 6 MG ground storage tank.
• The contract was awarded to Garney Companies Inc. for $84,121,405.00.
• The project includes pre-bid meetings, addenda, and bid results.