This bid tabulation documents the competitive bids received for the “Parrot Island Water Park Site Development” project, which calls for extensive concrete work, construction of a shed structure, and associated electrical installations on Parrot Island. Three contractors submitted bids ranging from roughly $1.75 M to $1.93 M, each also providing a separate Performance & Payment bond cost. The record shows the bid opening took place on March 5 2026 at 2:30 PM, witnessed by city officials, but does not disclose the award outcome, contract start/end dates, or detailed contact information for the issuing agency.
• Scope: Concrete, shed erection, and electrical systems for a new water‑park site.
• Financial scale: Total bid amounts between $1.75 M and $1.93 M.
• Competitive landscape: Three bidders—SSI Inc., Steve Beam Construction, and Royal Ridge Construction—competed in an open procurement.