The City of Rapid City's Water Reclamation Division is bidding on miscellaneous facility projects, including the replacement of two boilers for the digester facility. The project has an engineer's estimate of $250,000.00, and the winning bid was $277,600.00 by G+ R Controls. The project involves pre-purchasing boiler equipment due to a long lead time. Key aspects of the project include:
• Replacement of two boilers for the digester facility
• Pre-purchasing of boiler equipment due to long lead time
• Engineer's estimate of $250,000.00
• Winning bid of $277,600.00 by G+ R Controls