The contract is for the SRWTP Feed Line Restoration project, which includes the installation of a concrete cradle for the 24” feed line at the South Regional Water Treatment Plant. The project also involves the removal and replacement of a 24” butterfly valve, site restoration, and the installation of new bollards, landscape rock, weed fabric, and asphalt concrete with curbing. The contractor awarded the contract is A.C. Schultes of Florida, Inc.
• The project location is SRWTP, 250 Osmosis Drive, Bldg B, Palm Bay, Florida 32909.
• The bid submission date was May 21, 2019, at 5:00:00 PM EDT.
• The bid posting date was April 25, 2019, at 4:59:53 PM EDT.
• A pre-bid conference was held on May 9, 2019, at 10:00:00 AM EDT.
• The contract amount is $65,645.00.