The contract is for the construction of the Hawks Nest State Park Tramway Upper and Lower Terminal. The contract was awarded to BPI, Inc. and has a total order amount of $2,400,000. The contract start date is April 22, 2025, and the end date is September 18, 2025. The scope of work includes the construction of the tramway terminal. Some key points about this contract include:
• The contract is a change order to establish the contract start date.
• The contract has a total order amount of $2,400,000.
• The contract start date is April 22, 2025, and the end date is September 18, 2025.
• The scope of work includes the construction of the tramway terminal.
• The contract was awarded to BPI, Inc.
• The points-of-contact for the contract are Joseph (Josh) E Hager III, James H Adkins, and Christian Wells.