The contract involves the reconstruction of sewer, water, and streets, as well as the construction of drainage improvements. The project includes grading work and improvements to Robbinsdale Park. The contract was awarded to multiple vendors, with a total base bid of $4,937,000.00. The scope of work includes the reconstruction of E. Idaho Street, E. Nevada Street, and Ivy Avenue Street, as well as the construction of drainage improvements for the Meade/Hawthorne Drainage Element 221. The contract also includes add-on alternates and bond requirements.
• The contract involves multiple vendors, each with their own base bid and add-on alternates.
• The project includes grading work and improvements to Robbinsdale Park.
• The contract has a total base bid of $4,937,000.00.
• The scope of work includes the reconstruction of streets and the construction of drainage improvements.
• The contract includes add-on alternates and bond requirements.