The contract is for the replacement of water pipes on Seneca Pl, Terracegreen Pl, and Birdie Dr. The work includes constructing approximately 1,140 linear feet of 8-inch and 6-inch ductile iron waterline with fittings, valves, thrust blocking, service laterals, air release valves, blow-off assemblies, fire hydrants, and required appurtenances. The contract also includes restoring surfaces, abandoning old utilities, and other work as shown on the plans or described in the contract documents. The engineering estimates for the project are: Schedule ‘A’ - $435,000; Schedule ‘B’ - $245,000; and Schedule ‘C’ - $160,000.
• The contract was awarded to multiple vendors, including Turney Excavating, Riverbend Construction, Inc., North Santiam Paving Co., Trench Line Excavation Inc., Pacific North Construction, LLC, Wildish Construction Co.
• The point-of-contact person listed is Josh Bjornstedt, Project Manager, and also Katy Sproat, Public Works Department.
• The contract is subject to ORS 279C.800 to 279C.870.
• The City encourages small, minority- and women-owned businesses to bid.