The contract is for the demolition of the former police station and jail located at 116 N Main Avenue in Ridgefield, Washington. The contractor will be responsible for the removal of approximately 10,215 square feet of asphalt pavement, safe handling and disposal of materials with lead-based paint, re-grading after building and pavement removal, and restoration of the property to approximately the same grade with fresh gravel as needed. The contract was awarded to Raz Construction Co. for a total of $45,654. The project started on June 24, 2024, and was completed on July 3, 2024.
• The contract includes the demolition of the old police building and jail.
• The contractor is responsible for the removal of asphalt pavement and re-grading of the property.
• The contract value is $45,654.
• The project was completed in 9 days.
• The contractor did not hire any subcontractors for this project.