The contract is for the replumbing of leachate tanks at the Kiefer Landfill, Unit 2. The work includes replacing existing PVC pipes and valves. The estimated construction cost is $72,000, and a California contractor's license is required. The bid was submitted by BWD Construction Inc, and the contract was awarded to this vendor. The scope of work includes mobilization and demobilization, equipment installation, and the replacement of various valves and pipes.
• The contract requires a non-mandatory pre-bid conference.
• The bid security must be a bidder's bond, a certified check, or cash.
• The subcontractor listing includes Telstar Instruments for electrical work.
• The contract is subject to the Subletting and Subcontracting Fair Practices Act.