This contract concerns the design‑build construction of the South Hartford Conveyance and Storage Tunnel Arlington, Newington and New‑Britain Consolidation Conduits. The scope includes excavation and installation of large‑diameter conduits, associated diversion structures, high‑outlet relief structures, and two odor‑control facilities, plus all related equipment, permits, and testing. The work is funded by the Connecticut Department of Energy and Environmental Protection (DEEP) Clean Water Fund and must comply with state and federal minority‑business participation requirements.
• Full bid package available through MDC’s e‑bid portal; mandatory pre‑bid conference held August 2 2019.
• Requires a current DAS Contractor Pre‑qualification Certificate for tunnelling or sewer/water lines, and a 10 % bid security.
• All work to be performed within the City of Hartford and Town of West Hartford.
Attached files
The award documents live at the source — open the contract source above to download them.